AB748, s. 31 17Section 31. 196.49 (3) (b) (intro.), 2. and 3. of the statutes are amended to read:
AB748,18,2218 196.49 (3) (b) (intro.) Except as provided in par. pars. (d) and (e), the
19commission may require by rule or special order under par. (a) that no project may
20proceed until the commission has certified that public convenience and necessity
21require the project. The commission may refuse to certify a project if it appears that
22the completion of the project will do any of the following:
AB748,18,2423 2. Provide facilities unreasonably in excess of the probable future requirements
24needs of the public.
AB748,19,4
13. When placed in operation, add to the cost of service without proportionately
2increasing the value or available quantity of service to customers that the public
3utility has a duty to serve
unless the public utility waives consideration by the
4commission, in the fixation of rates, of such consequent increase of cost of service.
AB748, s. 32 5Section 32. 196.49 (3) (e) of the statutes is created to read:
AB748,19,106 196.49 (3) (e) 1. A public utility that provides electric service is not required to
7obtain commission certification under par. (b) for a project proposed by the public
8utility, other than the construction of a nuclear power plant, as defined in s. 196.493
9(1), that has a cost that is less than any of the following amounts, as annually
10adjusted for inflation by the commission in rules promulgated under subd. 2.:
AB748,19,1211 a. If the public utility's annual gross operating revenues are less than
12$5,000,000, $100,000.
AB748,19,1513 b. If the public utility's annual gross operating revenues are not less than
14$5,000,000 nor more than $250,000,000, 2% of the public utility's annual gross
15operating revenues.
AB748,19,1716 c. If the public utility's annual gross operating revenues are more than
17$250,000,000, $5,000,000.
AB748,19,2018 2. The commission shall promulgate rules that establish requirements for
19determining a public utility's annual gross operating revenues for purposes of subd.
201. and for annually adjusting the amounts specified in subd. 1. for inflation.
AB748, s. 33 21Section 33. 196.491 (title) of the statutes is amended to read:
AB748,19,23 22196.491 (title) Advance planning of electric Strategic energy
23assessment; electric
generating facilities and transmission lines.
AB748, s. 34 24Section 34. 196.491 (1) (a) of the statutes is repealed.
AB748, s. 35 25Section 35. 196.491 (1) (am) of the statutes is created to read:
AB748,20,1
1196.491 (1) (am) "Affiliated interest" has the meaning given in s. 196.52 (1).
AB748, s. 36 2Section 36. 196.491 (1) (bm) of the statutes is created to read:
AB748,20,53 196.491 (1) (bm) "Cooperative association" means a cooperative association
4organized under ch. 185 for the purpose of generating, distributing or furnishing
5electric energy at retail or wholesale to its members only.
AB748, s. 37 6Section 37. 196.491 (1) (d) of the statutes is amended to read:
AB748,20,147 196.491 (1) (d) "Electric utility" means any public utility, as defined in s.
8196.01, which is involved in the generation, distribution and sale of electric energy,
9and any corporation, company, individual or association, and any cooperative
10association organized under ch. 185 for the purpose of generating, distributing or
11furnishing electric energy at retail or wholesale to its members only
, which owns or
12operates, or plans within the next 10 3 years to construct, own or operate, bulk
13electric generating facilities, large electric generating
facilities or high-voltage
14transmission lines
in the state.
AB748, s. 38 15Section 38. 196.491 (1) (e) of the statutes is amended to read:
AB748,20,1716 196.491 (1) (e) "Facility" means a bulk electric generating facility, a large
17electric generating facility or a high-voltage transmission line.
AB748, s. 39 18Section 39. 196.491 (1) (f) of the statutes is amended to read:
AB748,20,2419 196.491 (1) (f) Except as provided in subs. (2) (b) 8. and (3) (d) 3m.,
20"high-voltage transmission line" means a conductor of electric energy exceeding one
21mile
5 miles in length designed for operation at a nominal voltage of 100 kilovolts or
22more, together with associated facilities, and does not include transmission line
23relocations that the commission determines are necessary to facilitate highway or
24airport projects.
AB748, s. 40 25Section 40. 196.491 (1) (g) of the statutes is amended to read:
AB748,21,3
1196.491 (1) (g) "Large electric generating facility" means electric generating
2equipment and associated facilities designed for nominal operation at a capacity of
3between 12,000 and 300,000 50,000 kilowatts or more.
AB748, s. 41 4Section 41. 196.491 (1) (p) of the statutes is created to read:
AB748,21,65 196.491 (1) (p) "Public utility affiliate" has the meaning given in s. 196.795 (1)
6(L).
AB748, s. 42 7Section 42. 196.491 (1) (w) of the statutes is created to read:
AB748,21,118 196.491 (1) (w) "Wholesale merchant plant" means electric generating
9equipment and associated facilities located in this state that are owned and operated
10by a person that is not a public utility, public utility affiliate, affiliated interest or
11cooperative association and that does not provide service to any retail customer.
AB748, s. 43 12Section 43. 196.491 (2) (title) of the statutes is repealed and recreated to read:
AB748,21,1313 196.491 (2) (title) Strategic energy assessment.
AB748, s. 44 14Section 44. 196.491 (2) (a) (intro.) of the statutes is repealed and recreated to
15read:
AB748,21,1916 196.491 (2) (a) (intro.) The commission shall prepare an annual strategic
17energy assessment that evaluates the adequacy and reliability of the state's current
18and future electrical supply. The strategic energy assessment shall do all of the
19following:
AB748, s. 45 20Section 45. 196.491 (2) (a) 1. and 2. of the statutes are repealed.
AB748, s. 46 21Section 46. 196.491 (2) (a) 3. of the statutes is amended to read:
AB748,22,622 196.491 (2) (a) 3. Identify the location of proposed and alternative specific sites
23for all bulk electric generating facilities and all
and describe large electric generating
24facilities over 200,000 kilowatts for which a certificate of public convenience and
25necessity has not been applied for under sub. (3) but the commencement of whose

1construction is planned within 3 years, or such longer period as the commission
2deems necessary and indicate the impacts of the proposed and alternative
3generating facilities on the environment and the means by which potential adverse
4effects on such values will be avoided or minimized;
on which an electric utility plans
5to commence construction within 3 years and wholesale merchant plants on which
6a person plans to commence construction within 3 years.
AB748, s. 47 7Section 47. 196.491 (2) (a) 3g. of the statutes is created to read:
AB748,22,98 196.491 (2) (a) 3g. Assess the adequacy and reliability of purchased generation
9capacity and energy to serve the needs of the public.
AB748, s. 48 10Section 48. 196.491 (2) (a) 3m. of the statutes is amended to read:
AB748,22,1511 196.491 (2) (a) 3m. Identify the location of tentative and alternative routes for
12and describe high-voltage transmission lines on which an electric utility plans to
13commence
construction is intended to be commenced in the succeeding within 18
14months and indicate the effects of such transmission lines on the environment and
15the means by which potential adverse effects will be avoided or minimized;
.
AB748, s. 49 16Section 49. 196.491 (2) (a) 3r. of the statutes is created to read:
AB748,22,1917 196.491 (2) (a) 3r. Identify and describe any plans for assuring that there is an
18adequate ability to transfer electric power into the state and the transmission area,
19as defined in s. 196.48 (1) (b), in a reliable manner.
AB748, s. 50 20Section 50. 196.491 (2) (a) 4. of the statutes is amended to read:
AB748,22,2221 196.491 (2) (a) 4. Indicate in detail Identify and describe the projected demand
22for electric energy and the basis for determining the projected demand ;.
AB748, s. 51 23Section 51. 196.491 (2) (a) 5. and 6. of the statutes are repealed.
AB748, s. 52 24Section 52. 196.491 (2) (a) 7. of the statutes is amended to read:
AB748,23,2
1196.491 (2) (a) 7. Identify and describe existing and planned programs and
2policies
activities to discourage inefficient and excessive power use; and.
AB748, s. 53 3Section 53. 196.491 (2) (a) 8. of the statutes is repealed.
AB748, s. 54 4Section 54. 196.491 (2) (a) 9. to 13. of the statutes are created to read:
AB748,23,65 196.491 (2) (a) 9. Identify and describe existing and planned generating
6facilities that use renewable sources of energy.
AB748,23,97 10. Consider the public interest in economic development, public health and
8safety, protection of the environment and diversification of sources of energy
9supplies.
AB748,23,1110 11. Assess the extent to which the regional bulk-power market is contributing
11to the adequacy and reliability of the state's electrical supply.
AB748,23,1312 12. Assess the extent to which effective competition is contributing to a reliable,
13low-cost and environmentally sound source of electricity for the public.
AB748,23,1514 13. Assess whether sufficient electric capacity and energy will be available to
15the public at a reasonable price.
AB748, s. 55 16Section 55. 196.491 (2) (ag) of the statutes is created to read:
AB748,23,1917 196.491 (2) (ag) The commission shall promulgate rules that establish
18procedures and requirements for an electric utility to report information that is
19necessary for the commission to prepare strategic energy assessments under par. (a).
AB748, s. 56 20Section 56. 196.491 (2) (am) of the statutes is renumbered 196.491 (2r) and
21amended to read:
AB748,24,222 196.491 (2r) (title) Local ordinances. No local ordinance may prohibit or
23restrict testing activities undertaken by a an electric utility for purposes of preparing
24advance plans or
determining the suitability of a site for the placement of a facility.

1Any local unit of government objecting to such testing may petition the commission
2to impose reasonable restrictions on such activity.
AB748, s. 57 3Section 57. 196.491 (2) (b) (intro.) of the statutes is repealed and recreated to
4read:
AB748,24,75 196.491 (2) (b) (intro.) On or before July 1, the commission shall issue a draft
6of the annual strategic energy assessment that it prepares under par. (a) to each of
7the following:
AB748, s. 58 8Section 58. 196.491 (2) (b) 8. of the statutes is amended to read:
AB748,24,129 196.491 (2) (b) 8. The lower Wisconsin state riverway board if the plan draft
10includes an assessment of the construction, modification or relocation of a
11high-voltage transmission line, as defined in s. 30.40 (3r), that is located in the lower
12Wisconsin riverway as defined in s. 30.40 (15).
AB748, s. 59 13Section 59. 196.491 (2) (b) 9. of the statutes is created to read:
AB748,24,1514 196.491 (2) (b) 9. Each electric utility that is required to report information to
15the commission under the rules promulgated under par. (ag).
AB748, s. 60 16Section 60. 196.491 (2) (c) and (d) of the statutes are repealed.
AB748, s. 61 17Section 61. 196.491 (2) (e) of the statutes is amended to read:
AB748,24,2118 196.491 (2) (e) Any state agency, as defined in s. 16.375 (1), county,
19municipality, town or person may submit written comments on any plan to the
20commission on a strategic energy assessment within 180 90 days after the plan is
21filed
copies of the draft are issued under par. (b).
AB748, s. 62 22Section 62. 196.491 (2) (f) of the statutes is amended to read:
AB748,25,1723 196.491 (2) (f) Because the planning process for facilities siting otherwise
24incorporates consideration and analysis of environmental impact, s.
Section 1.11 (2)
25(c) shall not apply to advance plans a strategic energy assessment prepared under

1par. (a) but the commission shall prepare a single environmental assessment on all
2plans submitted for approval under par. (a)
the strategic energy assessment, which
3shall include a discussion of generic issues related thereto. Such and environmental
4impacts. The commission shall make the environmental
assessment shall be made
5available to the public at least 30 days prior to the hearing under par. (g). The
6assessment on the plans is different from an environmental impact statement on a
7particular facility in that it need not identify the environmental effects of proposed
8sites for facilities in the plan with the same degree of detail as is required when a
9particular facility is considered for a certificate of public convenience and necessity
10under sub. (3). The assessment need not repeat information included in an
11assessment prepared for a plan submitted under par. (a) on a prior reporting date and
12with respect to which no material additional data is required or as to which there has
13been no material change in circumstances. Applicable portions of such assessment
14may be included by reference in any environmental impact statement prepared by
15the commission, including a statement prepared in connection with the
16consideration of an application for a certificate of public convenience and necessity
17under sub. (3).
AB748, s. 63 18Section 63. 196.491 (2) (g) of the statutes, as affected by 1997 Wisconsin Act
1935
, is amended to read:
AB748,26,2020 196.491 (2) (g) Within 180 No sooner than 30 and no later than 90 days after
21the plan is filed copies of the draft are issued under par. (b), the commission shall hold
22a hearing thereon on the draft which may not be a hearing under s. 227.42 or 227.44.
23The hearing shall be held in an administrative district, established by executive
24order 22, issued August 24, 1970, which the commission determines will be
25significantly affected by facilities proposed in the plan to be constructed in the

1following
on which an electric utility plans to commence construction within 3 years.
2The commission may thereafter adjourn the hearing to other locations or may
3conduct the hearing by interactive video conference or other electronic method.
4Notice of such hearing shall be given by class 1 notice, under ch. 985, published in
5the official state newspaper and such other regional papers of general circulation as
6may be designated by the commission. At such hearing the commission shall briefly
7describe the plan strategic energy assessment and give all interested persons an
8opportunity, subject to reasonable limitations on the presentation of repetitious
9material, to express their views on any aspect of the plan. The presentation of such
10views need not be under oath nor subject to cross-examination. The commission
11shall advise all persons present of their right to express their views orally or in
12writing, under oath or otherwise, and of the legal effect of each such form of testimony

13strategic energy assessment. A record of unsworn testimony the hearing shall be
14made and considered by the commission as comments on the plan strategic energy
15assessment
under par. (e). Persons presenting such views shall not be parties. The
16utility, any state agency, county, municipality, town, or any person whose substantial
17rights may be adversely affected by the testing for or construction of facilities
18described in an advance plan, shall, upon filing written notice setting forth its
19interest at least 10 days in advance, be afforded all the rights of a party in a contested
20case.
AB748, s. 64 21Section 64. 196.491 (2) (gm) of the statutes is created to read:
AB748,27,222 196.491 (2) (gm) Based on comments received on a draft, the commission shall
23prepare a final strategic energy assessment within 90 days after a hearing under par.
24(g). The commission shall provide copies of the final strategic energy assessment to

1any state agency, county, municipality, town or other person who submitted
2comments on the draft under par. (e) and to the persons specified in par. (b).
AB748, s. 65 3Section 65. 196.491 (2) (i) to (m) of the statutes are repealed.
AB748, s. 66 4Section 66. 196.491 (2m) (title) of the statutes is repealed.
AB748, s. 67 5Section 67. 196.491 (2m) of the statutes is renumbered 196.491 (3) (a) 3. a. and
6amended to read:
AB748,28,27 196.491 (3) (a) 3. a. At least 120 days prior to the filing of an application for a
8certificate of public convenience and necessity under sub. (3) for a bulk or large
9electric generating facility, the applicant shall notify the department and the
10commission of its intention to make such application and
At the same time that a
11person files an application under subd. 1., the person shall
provide the department
12with an engineering plan showing the location of the facility, a description of the
13facility, including the major components thereof having of the facility that have a
14significant air, water or solid waste pollution potential, and a description of the
15anticipated effects of such the facility on air and water quality. Within 60 30 days
16thereafter after a person provides an engineering plan, the department shall provide
17the applicant person with a listing of each department permit or approval which, on
18the basis of the information contained in the engineering plan, appears to be required
19for the construction or operation of the facility. The department shall, in consultation
20with the commission, also designate which permits and approvals, or portions
21thereof, must be obtained prior to the issuance of the certificate of public convenience
22and necessity. Such designation shall be based on a finding by the department that
23the granting or denial of the same could significantly affect overall facility design or
24location. At any time prior to the issuance of the certificate of public convenience and

1necessity, the department may, in consultation with the commission, waive the
2necessity of obtaining any such permit or approval in advance of such certificate.
AB748, s. 68 3Section 68. 196.491 (3) (a) of the statutes is renumbered 196.491 (3) (a) 1. and
4amended to read:
AB748,28,235 196.491 (3) (a) 1. No person may commence the construction of a facility unless
6such the person has applied for and received a certificate of public convenience and
7necessity from the commission as provided in this section. An application in the form
8and containing the information required by commission rules for such certificate
9shall be filed with the commission not less than 18 months prior to the
10commencement of construction of a bulk electric generating facility, and not less than

116 months prior to the commencement of construction of a large electric generating
12facility or a high-voltage transmission line. Within 10 days after filing the
13application, the commission shall send a copy of the application to the clerk of each
14municipality and town in which the proposed facility is to be located and to the main
15public library in each such county. The applicant shall apply for any permits or
16approvals required by the department prior to the issuance of a certificate of public
17convenience and necessity within 20 days after the application to the commission.
18An applicant shall make a preliminary application for all other permits and
19approvals specified under sub. (2m). Such preliminary application shall be sufficient
20if it identifies the permits and approvals applied for and contains so much of the
21information required for each such permit or approval as is then available to the
22applicant. Thereafter the applicant shall supply necessary additional engineering
23and design information as it becomes available.
AB748, s. 69 24Section 69. 196.491 (3) (a) 2. of the statutes is created to read:
AB748,29,9
1196.491 (3) (a) 2. The commission shall determine whether an application filed
2under subd. 1. is complete and, no later than 30 days after the application is filed,
3notify the applicant about the determination. If the commission determines that the
4application is incomplete, the notice shall state the reason for the determination. An
5applicant may supplement and refile an application that the commission has
6determined to be incomplete. There is no limit on the number of times that an
7applicant may refile an application under this subdivision. If the commission fails
8to determine whether an application is complete within 30 days after the application
9is filed, the application shall be considered to be complete.
AB748, s. 70 10Section 70. 196.491 (3) (a) 3. b. of the statutes is created to read:
AB748,29,2411 196.491 (3) (a) 3. b. Within 20 days after the department provides a listing
12specified in subd. 3. a. to a person, the person shall apply for the permits and
13approvals identified in the listing. The department shall determine whether an
14application under this subd. 3. b. is complete and, no later than 30 days after the
15application is filed, notify the applicant about the determination. If the department
16determines that the application is incomplete, the notice shall state the reason for
17the determination. An applicant may supplement and refile an application that the
18department has determined to be incomplete. There is no limit on the number of
19times that an applicant may refile an application under this subd. 3. b. If the
20department fails to determine whether an application is complete within 30 days
21after the application is filed, the application shall be considered to be complete. The
22department shall complete action on an application under this subd. 3. b. within 90
23days after the date on which the application is determined or considered to be
24complete.
AB748, s. 71 25Section 71. 196.491 (3) (b) of the statutes is amended to read:
AB748,30,4
1196.491 (3) (b) The commission shall hold a public hearing on the an
2application that is determined or considered to be complete in the area affected
3pursuant to s. 227.44. A class 1 notice, under ch. 985, shall be given at least 30 days
4prior to the hearing.
AB748, s. 72 5Section 72. 196.491 (3) (d) (intro.) of the statutes is amended to read:
AB748,30,96 196.491 (3) (d) (intro.) Except as provided under par. (e) and s. 196.493, the
7commission shall approve an application for a certificate of public convenience and
8necessity shall be approved only if the commission determines that all of the
9following
:
AB748, s. 73 10Section 73. 196.491 (3) (d) 1. of the statutes is repealed.
AB748, s. 74 11Section 74. 196.491 (3) (d) 2. of the statutes is amended to read:
Loading...
Loading...